Boiler Repair following tube rupture
Radiant Superheater Replacement of 25 full boiler tubes
High-Temperature Superheater Replacement of 35 full tubes
Trash Burning Boiler Maintenance
Boiler Grate Maintenance
Replace Worn Grate Components During Plant Outage
Replace Trash Ram into Furnace
25 Tube Partial Replacements
Process Piping, ASME Welding Repair During Plant Outage
Unit#4, Boiler Outage Tube Sectional Replacement of 28 Tubes
Replaced Due to Hydrogen Embrittlement Found During Inspection of Original Tube Replacement
One Section of 1.5" Reheat Section of Boiler
100% Weld Acceptance
Replaced Cogen Economizer Header
125 Tube Connection Welds
Prefabricated Economizer Header