Construction Management

  • SUBSTATION CONSTRUCTION OVERSIGHT​

    Install foundation and containment ​

    Placement of the main primary transformer​

    Install substation control house​

    Install structural steel and dead-end structure ( “H” & A-frame )​

  • REFINERY

    Construction Management, Built Blast Resistant Module for Operations Shelter

    Built Concrete Foundation, 60” X 50”, 4 Feet Deep

    Set Four Blast Resistant Module, 52,000 Pounds Each

    Supervised Sewer Connections Supervised Electrical Power and Data Connection

    Conduit in Trenches and Overhead in Cable Trays 96 Strand Fiber Optic Cables

    •24 Strand Data Cables

    •Supervised Domestic Water Connection

  • CONSTRUCTION MANAGEMENT OVERSIGHT ​

    Client 50 mW site builds (3) ​

    Client 100 mW site builds (3) ​

    Client 200 / 400 mW site builds (2) ​

    Client 300 / 600 mW site builds (3) ​

    Client Substation & Interconnects builds ​

  • REFINERY

    Line 71/79

    Project Scope, designed two 12” carbon steel lines to provide flexibility between two local facilities AND main distribution line

    160 caissons throughout an existing storage tank facility

    Estimated and tracked man hours and costs to complete the project

    Developed an accurate projected schedule including coordinating tie ins with multiple operating unit outages.

    Constructability analysis

  • POWER GENERATION FACILITY

    Under Alloy Project and High Yield Crude and Vacuum Unit Upgrade

    Managed two projects in one operating unit

    Replaced main crude unit process piping

    Replaced vacuum vessel and associated process piping

    Scheduled 75% of construction completed pre turnaround

  • CHEMICAL PLANT

    Scrubber Installation Project

    125-Foot-tall fiberglass scrubber unit• Structural steel support structure, stairways and walkways to the top

    Fiberglass and steel piping systems

    Demolished an existing 200-foot-tall existing scrubber, steel construction